Walsh Service Solutions provided specialized safety oversight for a major federal marine infrastructure project at a century-old facility. Supporting the Kokosing-Alberici joint venture, our team ensured continuous safety compliance during the installation of a new upper approach wall.

Project Overview

  • Project Value: $77K

  • Timeline: 2022 – 2023

  • Location: Sault Ste. Marie, Michigan

  • Core Role: Night Shift Site Safety Officer

Project Scope & Operations

  • Approach Wall Installation: Supported the large-scale federal project to install a new upper approach wall, a critical component for vessel navigation and lock approach safety.

  • Safety Leadership: Served as the designated Night Shift Site Safety Officer, maintaining rigorous safety protocols during high-risk marine construction activities.

  • 24-Hour Operational Safety: Managed safety oversight during overnight shifts, addressing the unique challenges of low-visibility environments and remote site logistics.

  • Regulatory Compliance: Ensured all activities met strict federal and USACE safety standards at a 100+ year-old facility with complex historical infrastructure constraints.

The Result

Throughout the 2022–2023 project phases, WSS maintained a flawless safety record during night-shift operations. Our presence allowed for continuous, around-the-clock construction progress, ensuring the upper approach wall installation remained compliant with all federal health and safety regulations.