Vertical Construction – Sault Ste. Marie (2021)
Walsh Service Solutions provided critical specialized support for the rehabilitation of a century-old federal powerhouse. Working in a high-consequence industrial environment, our team integrated health and safety leadership with complex structural access solutions to facilitate the modernization of heavy lifting infrastructure.
Project Overview
-
Project Value: $264K
-
Timeline: 2021
-
Location: Sault Ste. Marie, Michigan
-
Facility Age: 100+ Years (Historic Federal Powerhouse)
Project Scope & Operations
-
Scaffolding Engineering & Support: Engineered, erected, and maintained extensive scaffolding systems to provide safe access for overhead works. Our team managed continuous modifications and final removal to accommodate the evolving needs of the heavy mechanical phase.
-
Crane Rail Rehabilitation: Supported the primary contractor, Ryba Marine, in the systematic removal and replacement of heavy-duty overhead crane rails along both the east and west corridors of the powerhouse.
-
Historic Facility Integration: Navigated the unique challenges of a 100+ year-old structure, implementing vibration-sensitive and non-destructive access methods to protect the facility’s legacy while enabling modern upgrades.
The Result
By providing a seamless blend of safety expertise and robust access infrastructure, WSS enabled the successful replacement of the facility’s crane rails. Our presence ensured that the high-risk vertical work was performed without incident, preserving the structural integrity of the historic powerhouse while restoring its essential heavy-lifting capabilities.






